Statutory default gates

A statutory default gate is a waiting period the law puts between a missed payment and a lender acting on it. The Statutory Default Gates tab under Settings lists the gates your organisation has configured, one row per regulatory regime.

For what the gates do to an account, see chasing arrears. This article explains the tab itself.

What a row holds

Column What it tells you
Regime The regulatory regime the row applies to
Effective From The first day the row applies
Notice After (business days) Waiting period before a notice may be issued
Enforce After (business days) Waiting period after despatch before enforcement may begin
Calendar The business calendar both periods are counted on

Each period counts business days on the named calendar. Weekends and the calendar’s public holidays do not count. See business day conventions.

Which standard the rows implement

In South Africa the National Credit Act sets these gates. Two rows of our standards register apply:

Both rows are recorded as partial. Only the email channel is proven, and the notice wording is not lawyer-reviewed. Chasing arrears explains what that means for you.

How the periods are counted

The first period runs from the oldest unpaid amount. The second runs from despatch of the notice.

Several rows can exist for one regime. They differ by Effective From. The row with the latest date on or before the day being checked applies. A change in the law is therefore a new dated row, not an edit to the old one.

A regime with no row has no statutory process. Its accounts never become eligible for a notice.

A worked example

The South African retail template (za-retail) seeds one NCA row. It is dated 1 January 2000, with 20 business days to notice and 10 to enforcement, on the South Africa calendar. The row is in tenant-templates/regimes/za-nca/retail-bank/DefaultProcessSettings.yaml.

Alex’s oldest unpaid amount fell due on 1 June 2026. The calendar works Monday to Friday.

  1. Count 20 business days from 1 June 2026. The twentieth is 29 June 2026.
  2. On 28 June the account is not eligible. On 29 June it is.
  3. Add one public holiday on 26 June. The twentieth business day becomes 30 June.

The row is unchanged in step 3. Only the calendar changed.

What your organisation configures

The whole capability switches off per tenant. See switching features on and off.

From the LedgerTM product guide, as shipped with the software and written with it. Copied from the platform repository on 2026-11-11.